1. What is the expected out turn of cement concrete 1 : 2 :
4 per mason per day is?
-
m3
m^3
2. Damp Proof Course is measure in__________
Since thickness of DPC is small.
3. Plinth area of a building will not include which of the following?
Courtyards are also excluded in plinth area.
4. What is the useful or livable area of a building known?
Carpet area.
5. Initial lead for earthwork in foundation trench is_________
Initial lead is 50m and initial lift is 1.5m.
6. When filling work in trech is done, the thickness of each layer of fill should not be more than
7. The excavation exceeding 1.5m width and 10sqm in plan area and depth not exceeding 30cm can be called as____________
Surface excavation.
8.In which of the following cases measurments are made in sqm?
Sqm for Surface dressing upto 15cm and surface excavation upto 30cm .
9. Budget coasting for construction projesct should be due
in planning stage.
10. Material shall be issued on the basis of which of the following
Index form.